Construction of the Bartogay HPP-28 on the Shelek River, Almaty Region, Enbekshikazakh District
Construction of the Bartogay HPP-28 on the Shelek River, Almaty Region, Enbekshikazakh District
The project envisages the construction of a small hydroelectric power plant (HPP) with an installed capacity of 3.3 MW on the Bartogay reservoir in the Enbekshikazakh district of the Almaty region. The maximum power generation capacity is 14,256,000 kWh.
- Indicator Results
- Investment amount, thousand US dollars 2 951
- NPV of the Project thousand, US dollars 964
- IRR, % 28
- EBITDA yield, %
- Payback period, years 9,64